IIBA CCBA Übungsprüfungen
Zuletzt aktualisiert am 27.04.2025- Prüfungscode: CCBA
- Prüfungsname: Certification of Competency in Business Analysis
- Zertifizierungsanbieter: IIBA
- Zuletzt aktualisiert am: 27.04.2025
After a number of requirements elicitation workshops, the business analyst (BA) notices that two business stakeholders did not speak up during any of the discussions.
What should the BA do in the next workshop?
- A . Allow only the two stakeholders to speak so that other stakeholders hear their input.
- B . Ask all attendees for their input, ensuring that each stakeholder is given time to speak and provide their opinion.
- C . Omit the two stakeholders from the next meeting since they do not seem to be engaged.
- D . Proceed as normal, assuming that the two business stakeholders will speak up if and when they are ready.
A business analyst (BA) is designing solutions for a set of requirements and finds that there is an opportunity to improve the operations of the business.
Which of the following is an opportunity for improvement the BA could recommend?
- A . Create a solution by constructing a number of solution components to meet the requirements
- B . Enable the solutions that will satisfy the highest priority requirements and stakeholder needs
- C . Provide information to staff so they can answer customer inquiries directly themselves
- D . Purchase software that contains features that are not currently required but are included for free
Which one of the following business analysis techniques for analyzing business goals converts the business goals into achievable objectives and measures?
- A . Benchmarking
- B . Root cause analysis
- C . Functional decomposition
- D . Business rules analysis
A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture theinformation in standardized templates, and ensure that all activities are identified first and then divided into tasks.
Which approach provides the appropriate level of formality for this project?
- A . Reactive
- B . Adaptive
- C . Proactive
- D . Predictive
The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items.
What should the business analyst (BA) do to help move the project forward?
- A . Schedule a backlog walkthrough with the two stakeholders
- B . Confirm the authority of the two stakeholders
- C . Notify the project manager
- D . Apply the previous backlog priority
A project is being initiated to enhance an online product because sales have declined for over a year. The company leaders are confident that all of the skills needed to improve the product exist within the company. By enhancing the product, sales will increase, and new customers will emerge.
A business analyst (BA) will help the enhancement project by first:
- A . Identifying the stakeholders
- B . Implementing a suitable solution
- C . Documenting the requirements
- D . Evaluating the business need
Linda works as a project manager for an IT project. She is getting new developers for completing her project.
Which of the following processes is she involved in?
- A . Manage Project Team
- B . Develop Project Team
- C . Acquire Project Team
- D . Human Resource Planning
During a senior management meeting about a project at the requirements analysis stage, a business analyst (BA) stated that there were a number of workarounds associated with the current application. The Chief Information Officer (CIO) was looking for ways to improve the situation, and the BA suggests a solution.
Which of the following can the BA suggest that the organization consider to increase efficiencies?
- A . Strategic realignment
- B . Capability assessment
- C . Project abandonment
- D . Process improvement
Which stakeholder in the solution assessment task will provide information on technical constraints that could limit the solutions that may be implemented?
- A . Project manager
- B . Suppliers
- C . Sponsor
- D . Operational support
The Business Requirements Document (BRD) prepared by the business analyst (BA) was circulated to stakeholders for approval. Some stakeholders objected to the Use Case diagrams and could not understand them.
Why would these be included in the document?
- A . The models were included as a mistake because Use Case diagrams are technical.
- B . The models are part of the technical documents and not part of BRD documents.
- C . The models are used for analysis and refining requirements and design.
- D . The models did not change the value compared to text-based requirements